The report presents the findings of an investigation into the freeboard cooler failure, in November 1981. The freeboard cooler was installed in the freeboard zone at the top of the combustor and the design intent was to operate so as to ensure the off-gas temperature did not exceed 900/sup 0/C. During Test Series One, the freeboard temperature never reached 900/sup 0/C, but the cooler was operated to reduce the exit flue gas temperature from the main heat exchanger to below the maximum allowable working temperature of the ductwork downstream of the exchanger. The cooler failed when several cracks appeared on bends in the air space between the combustor pressure shell and furnace water wall. A description of the cooler is provided along with details of its function, design, fabrication, commissioning and operation. The failure is described, and causes of failure are discussed. The report concludes that the failure occurred due to stress corrosion cracking.

Data and Resources

Field Value
Citation "\"Not Available\""
Is NETL associated "\"Yes\""
NETL Point of Contact "\"Roy Long\""
NETL Point of Contact's Email "\"Roy.long@netl.doe.gov\""
NETL program or project "\"KMD\""
Publication Date "\"3/1/1982\""
Groups
  • AmeriGEOSS
  • Global Provider
Tags
  • amerigeo
  • amerigeoss
  • ckan
  • edx
  • energy
  • energy-data-exchange
  • geo
  • geoss
  • global
  • kmd
isopen True
license_id other-open
license_title Other (Open)
metadata_created 2025-11-25T22:41:40.908664
metadata_modified 2025-11-25T22:41:40.908668
notes The report presents the findings of an investigation into the freeboard cooler failure, in November 1981. The freeboard cooler was installed in the freeboard zone at the top of the combustor and the design intent was to operate so as to ensure the off-gas temperature did not exceed 900/sup 0/C. During Test Series One, the freeboard temperature never reached 900/sup 0/C, but the cooler was operated to reduce the exit flue gas temperature from the main heat exchanger to below the maximum allowable working temperature of the ductwork downstream of the exchanger. The cooler failed when several cracks appeared on bends in the air space between the combustor pressure shell and furnace water wall. A description of the cooler is provided along with details of its function, design, fabrication, commissioning and operation. The failure is described, and causes of failure are discussed. The report concludes that the failure occurred due to stress corrosion cracking.