Mozambique - Urban Water

Overall Design: Mixed-Methods Performance Evaluation with three components: (1) Ex-post performance evaluation (2) Infrastructure Assessment (3) Outcomes Analysis

Exposure to treatment: Nampula city water supply system 69 months
Nampula city storm drains 67 months
EMUSANA 66 months
Nacala city water supply system 75 months
Nacala Dama 60 months
Mocuba water supply 69 months
Quelimane storm drains 67 months

Evaluation Questions: (1) Was the program implemented according to approved plans and budget? (2) As implemented, were the activities cost-effective? (3) Are the infrastructure investments operational and being appropriately maintained? (4)What were the effects of Urban Water Supply Activity on key outcomes (i.e., water supply, water supply reliability, water consumption and/or expenditure, malaria and diarrhea incidence)? (5) What was the effect of Urban Drainage and Sanitation Activity on key outcomes (drainage capacity, flood incidence, flood severity, malaria incidence)? (6) What was the effect of Capacity-Building Activity on sanitation service delivery? (7)What lessons can MCC or the GoM apply in future programs to program design, implementation, and sustainment of results?

Data and Resources

Field Value
accessLevel public
bureauCode {184:03}
catalog_@context https://project-open-data.cio.gov/v1.1/schema/catalog.jsonld
catalog_conformsTo https://project-open-data.cio.gov/v1.1/schema
catalog_describedBy https://project-open-data.cio.gov/v1.1/schema/catalog.json
identifier DDI-MCC-MOZ-URBANWATER-2019-v01
landingPage https://data.mcc.gov/evaluations/index.php/catalog/234
license https://data.mcc.gov/terms-and-conditions.php
modified 2019-03-26
programCode {184:000}
publisher Millennium Challenge Corporation
resource-type Dataset
source_datajson_identifier true
source_hash cf1ccbd90772439d932b5584e15676edc32e8858
source_schema_version 1.1
Groups
  • AmeriGEOSS
  • National Provider
  • North America
Tags
  • amerigeo
  • amerigeoss
  • ckan
  • geo
  • geoss
  • mozambique
  • national
  • north-america
  • united-states
  • urban
  • wash
  • water
isopen False
license_id other-license-specified
license_title other-license-specified
maintainer Monitoring & Evaluation Division of the Millennium Challenge Corporation
maintainer_email impact-eval@mcc.gov
metadata_created 2025-11-20T11:46:42.697655
metadata_modified 2025-11-20T11:46:42.697659
notes Overall Design: Mixed-Methods Performance Evaluation with three components: (1) Ex-post performance evaluation (2) Infrastructure Assessment (3) Outcomes Analysis Exposure to treatment: Nampula city water supply system 69 months Nampula city storm drains 67 months EMUSANA 66 months Nacala city water supply system 75 months Nacala Dama 60 months Mocuba water supply 69 months Quelimane storm drains 67 months Evaluation Questions: (1) Was the program implemented according to approved plans and budget? (2) As implemented, were the activities cost-effective? (3) Are the infrastructure investments operational and being appropriately maintained? (4)What were the effects of Urban Water Supply Activity on key outcomes (i.e., water supply, water supply reliability, water consumption and/or expenditure, malaria and diarrhea incidence)? (5) What was the effect of Urban Drainage and Sanitation Activity on key outcomes (drainage capacity, flood incidence, flood severity, malaria incidence)? (6) What was the effect of Capacity-Building Activity on sanitation service delivery? (7)What lessons can MCC or the GoM apply in future programs to program design, implementation, and sustainment of results?
num_resources 4
num_tags 12
title Mozambique - Urban Water