This is the tenth technical progress report in connection with the Cooperative Agreement between DOE and Ohio Power Company for the Tidd PFBC Hot Gas Clean Up Test Facility. This report covers the period of work completed during the First Quarter of C 1992. Work focused on supporting field construction activities and expediting delivery of equipment. The project is on schedule. The following significant events occurred during this report period: The major components of the system were delivered to the site and installed: contract Modification No. 5 issued to Westinghouse authorized partial funding for proof-of-concept touting of an alternate filter candle material at Karhula, Finland; and contract Modification No. 2, issued to Babcock Wilcox covered additional material (hangers, steel) and certain work scope changes.